When should a job shop no-quote an RFQ?

No-quote an RFQ when the work does not fit your machines, materials or certifications, when you cannot make the date, when the package is too incomplete to price without guessing, or when that customer's RFQs never turn into orders. Decide in the first few minutes, before any estimating, and tell the buyer the same day.

Book a demo See the five questions

Why not quote everything?

Because estimating time is limited, and every hour spent on a quote you cannot win is an hour a winnable one waits. Speed matters: Modern Machine Shop's 2026 Top Shops survey found that shops quoting within a day won more new work than shops that took longer (source).

There is a second reason. The worst outcome is not losing a quote for work that does not suit you. It is winning it, at a price built on guesses, and finding out on the shop floor.

What are the signs of a poor fit?

  • The process or the size. The part needs a machine, a capacity or a material you do not run.
  • The tolerances. Tighter than you hold routinely, or tighter than you can measure.
  • The paperwork. A certification, registration or quality standard you do not hold.
  • The quantity. Ten thousand pieces sent to a prototype shop, or one piece sent to a production shop.
  • The date. A delivery you could only meet by pushing work you have already promised.
  • The package. Missing drawings, an old revision, no material or no quantity, and a buyer who does not answer questions.
  • The history. Many RFQs from this customer, no orders and no feedback on why.
  • The target price. A stated target below what the material alone will cost you.

The five questions to ask before estimating

Ask them in order, with the RFQ open and before anyone works out a time or a price. It takes a few minutes.

A five-question screen for an incoming RFQ
QuestionQuote itLook closerNo-quote
Fit: can we make it, in this material, to these tolerances, with the approvals asked for?It is work we do every weekOne operation would go to an outside supplierIt needs a process or an approval we do not have
Capacity: can we deliver by the date with the work already booked?YesOnly with overtime: offer a later dateNo date we could offer would be accepted
Information: are the drawings, revision, material, quantities and finish all here?YesSomething is missing: ask, or quote with the assumption written on the quoteThe missing piece decides the price and the buyer will not supply it
Customer: what happened to the last quotes we sent them, and do they pay?They order from usA new customer: quote, and note how it goesMany quotes and no orders, or a payment problem
Value: is the order worth the quoting time?YesSmall now, with a repeat likelyBelow our minimum charge, with no repeat in sight

A "no-quote" answer to any of the first three settles it: the shop cannot do the job, cannot do it in time, or cannot price it. The last two are judgment, and they are where your own records matter more than any rule.

How do you say no without losing the customer?

Reply the same day, name the part and revision, give the real reason in one sentence, and say what you would like to see instead. Three replies cover most cases:

  • The date. "Thank you for RFQ [number], part [number] rev [letter]. We are booked through [month] and could not meet your [date] delivery, so we are not quoting this one. If the date can move to [date], I can have a price to you by [day]."
  • The work. "Thank you for RFQ [number]. Part [number] rev [letter] needs [process, size or certification], which is outside what we do, so we are declining it instead of guessing at a price. We would be glad to quote your [the work you do]."
  • The package. "Before we can price part [number] rev [letter] we need [the material specification, the quantity, the missing drawing]. If you can send it by [day], we will have a quote to you by [day]."

The third is not a no. An RFQ with a gap in it is often worth one question before it is worth a decision.

Is a high price better than a no-quote?

Rarely. Quoting high to make a job go away still costs the estimating time. The buyer does not know it was a polite no and files you as expensive. And sometimes the order arrives anyway, for work you did not want, on a date you cannot meet. If the honest answer is no, say no. If the job is possible at a price that covers the risk, quote that price and write the reasons on the quote.

How do you know you are screening well?

Keep a log of every RFQ: the customer, the date in, the decision, the reason for any no-quote, the date the quote went out, and whether it was won or lost. Three figures come out of it:

  • Win rate by customer: orders ÷ quotes sent. A customer far below your average is using you to check someone else's price, or your price for their kind of work is off.
  • Time to quote: from the RFQ arriving to the quote going out. If it is creeping up, good RFQs are waiting behind poor ones.
  • Reasons for no-quotes: counted over a year, they show what work you keep turning away, which is the evidence for a machine, a certification or a hire.

When is it worth quoting anyway?

When the RFQ is a way in. A new customer's first RFQ tells you how they buy, even if you lose it. A part slightly outside your usual work, from a customer who orders regularly, can be worth the effort to keep the rest. In both cases quote it properly, state every assumption and exception on the quote, and note the result in the log so the next decision is easier.

Where does RobinQuote come in?

Some RFQs go unanswered only because nobody had the time. RobinQuote drafts a quote from the customer's PDF drawing in under a minute, on your own rates, for your estimator to check and send. When a quote takes minutes to check instead of being built by hand, fewer good RFQs have to be turned away for lack of time, and the screen above can be about fit, capacity and the customer. Those decisions stay with you.

Questions about no-quoting

Is it bad to no-quote an RFQ?

No. A quick, clear no lets the buyer move on and keeps you on their list for the work you do want. What damages the relationship is silence, or a quote that arrives after the order has gone elsewhere.

How fast should I reply if I am not quoting?

The same day if you can. The buyer has a deadline too, and an early no gives them time to find another supplier.

Should I give a reason for a no-quote?

Yes, in one honest sentence: the date, the process, the size, the certification or the missing information. A reason tells the buyer what to send you next time. Leave out anything about other suppliers or their prices.

How do I work out my quote win rate?

Orders won ÷ quotes sent over the same period, counted by number of quotes or by their value. Work it out for each customer as well as for the shop. There is no single good figure; compare it with your own past and look for the customers far below your average.